All Locations - Network Maintenance - 09/02/2019 - 09/06/2019

  • Friday, 30th August, 2019
  • 11:10am

We are scheduling the following maintenance for next week. See Below.

Affected Location: All Locations -  All services

Time Frame

Date: 09/02/2019 - 09/06/2019
Start Time: 9:00 AM EST
End Time:   5:00 PM EST

TYPE OF WORK: Core Routing Infrastructure Maintenance
PURPOSE OF WORK: Firmware and Security Updates
EXPECTED IMPACT: Between 5 to 15 minutes of actual downtime

We want to make you aware that this upcoming Monday (09/02) at 9 AM EST, there will be scheduled maintenance window for approximately 8 hours per day for the next 5 days. Our engineers will be performing upgrades to the core routers to improve stability and perform some regular maintenance. We do not expect any more than 15 minutes of downtime per VPS Node/Server during this window per day and there may not be any for some days. We are doing one router per day to minimize the impact at one time.

Currently we cannot give exact time/date about which VPS Node will be going down on which date as all VPS Nodes are distributed on multiple Core Routers, but none of VPS node should be going down for more then 15 minutes

If you have any questions regarding this maintenance please let us know.

 